Building Materials Engineering
We don't just transport equipment—we deliver on your global project commitments. In the building materials engineering sector, we leverage our experience across five continents to seamlessly connect China's manufacturing capabilities with global construction demands.
Mandalay Cement Factory, Myanmar
We implemented a port-to-door transport mission for 100,000 cubic meters of production line equipment, with the heaviest single piece weighing 106 tons. By implementing a dual-route solution integrating ocean freight, inland barging, and land transport, we delivered the cargo to the Kyaukse site with zero damage, ensuring the cement plant began operations on schedule.
Solution
|
Dual-route Transportation Plan two independent corridors (using various combinations of sea freight, inland barges, and land transport) as mutual backups to stagger the transport of key components, thereby reducing the risk of single-point failures. |
On-site Delivery Prioritize deliveries based on process priority. Schedule arrivals based on process priority, prepare on-site roads and lifting areas, and optimize temporary access routes to ensure immediate installation upon arrival. |
|
Schedule Assurance Dual-channel backups and milestone scheduling ensured the punctual arrival of critical equipment, supporting the cement factory's scheduled commissioning. |
Risk Mitigation Diversify risks across routes, ports, water levels, and road logistics. Heavy-lift engineering and professional reinforcement minimize handling and transport accident rates, achieving the goal of zero cargo damage. |